Illustrative image – not actual.NTPC has successfully tested impounding work for Phase-I of the Koldam hydel-based power plant in Bilaspur district of Himachal Pradesh.
The final impounding of the project will be started after the monsoon season, that is, by September 2014. Phase-I of the project entails a capacity of 200 MW.
The company is executing a 4 x 200 MW Koldam hydel project on River Satluj at a cost of Rs 6,000 crore.
The power plant is nearing completion. Major components of the project have already been constructed.
The reservoir impounding was started on 19 December 2013 to test bottom outlet gates and after that a technical expert advised implementation of additional work.
With completion of the impounding work as per the schedule, water was being held at 560 M level so that tunnel, dam and other components could be properly tested.