Illustrative image – not actual.NTPC has scrapped a contract with Punj Lloyd for its coal-based power project at Salakati, in Bongaigaon district of Assam, due to poor performance of the contractor.
The company had secured a contract worth Rs 210 crore in 2011. The scope of work involved underground civil work, piling and foundations for overground, civil, structural, and architectural work for the buildings, such as main plant, air washer, ESP control, service, mill, bunker and conveyor galleries, construction of the administration building and auditorium, the operation and maintenance workshop, and the CHP office-cum-workshop in the off-site area.
NTPC is implementing a 3 x 250 MW power plant which is estimated to cost Rs 4,375.35 crore.