NTPC Telangana Unit-2 successfully attains its full load capacityIllustrative image – not actual.

The Unit-2 of NTPC Telangana Super Thermal Power Project (TSTPP) successfully achieved full load of 800 MW on 03 February, 2024. The focus is on stabilisation activities and moving towards trial operation of the unit.

The TSTPP was taken up with a total power generation capacity of 1,600 MW (2x800 MW each) in the first phase, and with a total planned capacity of 4,000 MW near Ramagundam village in Karimnagar district. The project is based on the most efficient ultra super critical technology, and this marks a major milestone towrads making the state self-reliant in electricity. 

The Unit-2 thermal power project has been set up as part of the Andhra Pradesh Re-organisation Act 2014.

The 800 MW first unit was dedicated to the nation by Prime Minister Narendra Modi on 03 October, 2023.

 