Illustrative image – not actual.National Thermal Power Corporation
(NTPC) and the Pondicherry Government signed a power purchase agreement for
supply of power from NTPC’s Ramagundam (Stage III) project. The project is
coming up in the Karimnagar district of Andhra Pradesh.
As per the PPA, NTPC would be supplying
13 MW of power to Pondicherry. Currently, NTPC has an allocation of 10 MW from
Ramagundam (Stage II) and 50 MW from Stage I of the same project.
The Ramagundam Stage III project envisages
capacity expansion from 2,100 MW to 2,600 MW. The cost of the project, which is
Rs.1,818 crore, is being funded by a debt-equity ratio of 70:30.
Some other states that would benefit
from this project include Andhra Pradesh (146 MW), Karnataka (87 MW), Kerala
(61 MW).