Illustrative image – not actual.NTPC is all set to achieve an additional power generation capacity of 22,430 MW, targeted under the 11th Plan period. The corporation has an installed capacity of 29,894 MW at present.
Of the total planned target capacity, the company has already added 2,490 MW. Projects are underway to add another 16,180 MW of which 3,750 MW is being done through JV companies. Orders for the remaining capacity are scheduled to be placed by end November 2008.
In the current fiscal, NTPC plans to add 2,820 MW. Out of this, 750 MW has already been added; it comprises a 250 MW project in Bhilai and a 500 MW project at Sipat. The remaining capacity of 2,070 MW is being added at three locations - Sipat (1,320 MW), Bhilai (250 MW) and Kahalgaon (500 MW).