Illustrative image – not actual.NTPC has sought 525 acre of land from the Orissa government to build a water pipeline corridor for its 1,600 MW Super Thermal Power Project (STPP) located at Darlipalli, in Sundargarh district of the state.
The land is to be set aside in 21 villages spread across Sundargarh and Jharsuguda districts. It includes 278 acre private land, 195 acre government land and 52 acre of forest land.
The Water Resource Department, Orissa, has already given in-principle allocation of 160 cusec of water in favour of NTPC, from the Hirakud reservoir, for the Darlipalli plant.
The underground pipelines of 2 x 1,000 mm dia are to be laid from the Hirakud reservoir to the project site at Darlipalli through Jharsuguda district.
The company has secured coal linkages for the project from Dulanga block having a capacity of seven million tpa and Pakri Barwadih block with 12.5 million tpa capacity.