Illustrative image – not actual.NTPC has urged for environmental clearances from the Ministry of Environment & Forests (MoEF), for its Kaniha Open Cast project.
The company intended to commission the project in 2013, but due to delay in forest diversion and construction of Merry-Go-Round (MGR) system by the company, it is now expected to be commissioned by March 2015.
The stage-I forest clearance for the 171.15 ha land for the project is anticipated to be obtained by March 2014, and resettlement of project-affected families of Jarda village may also be done at the same time.
Against the estimated cost of Rs 457.77 crore for the Open Cast project, a cumulative expenditure of Rs 112.74 crore has been made as of May 2013. In FY14 (upto June), 0.500 million tonne of coal and 0.037 million cubic metre of OB was produced during the period.
Meanwhile, NTPC is also awaiting transfer of 109.69 acre of land for resettlement at village Takua for the project-affected people of Jarda village.