National Thermal Power Corporation (NTPC) has sought Rs.18,000 crore budgetary support from the Centre in the event of the Central Electricity Regulatory Commission's (CERC) new tariff order being implemented.
NTPC has stated that if CERC’s new tariff order on
availability based tariff was implemented then it would lead to a substantial reduction
in its internal resources. The total impact on the Corporation would
reportedly, amount to Rs.21,500 crore. This in turn would make it difficult for
NTPC to achieve its set target of 20,000 MW of additional generation capacity by
2012, compelling the Corporation to lower its target to 5,000 MW.
NTPC’s targeted 20,000 MW additional generation capacity is estimated to cost Rs.80,000 crore.