Illustrative image – not actual.National Thermal Power Corporation has revised upwards its total capacity target to be attained by March 2017. The company has targeted to reach total installed capacity of 66,000 MW by March 2017 (end of the XII Plan period) from the earlier 56,000 MW.
NTPC has also increased its capacity addition target for the XI Plan period (2007-12) from 11,558 MW to 17,052 MW.
NTPC is grooming itself into an "energy-chain" company rather than a power generation company. It is exploring the entire value chain from coal mining, gas exploration, LNG regasification. Even in the power sector, the company has diversified into hydropower generation. It may be mentioned here that the company has also proposed to change its name to NTPC Ltd, to reflect the imminent diversity in operations.
NTPC today has 20 coal and gas-fired plants with an aggregate capacity of around 24,000 MW.