NTPC revokes civil contracts for equipment supply delaysIllustrative image – not actual.

NTPC has reportedly cancelled civil work contracts for its projects in Assam and Uttarakhand.

The company has scrapped the work contracts of two contractors - SPML and a consortium of SSJV & ZVS owing to delays in equipment deliveries.

NTPC is setting up 750 MW (3x250) Bongaigaon thermal power project at Salakati in Assam. The offsite civil works were awarded to SPML Infra in April 2008.

The 520 MW Tapovan Vishnugad project is coming up across the River Dhauliganga in Chamoli district of Uttarakhand. In January 2007, NTPC had awarded the contract to construct a complex of hydro engineering structures of hydroelectric power station 'Tapowan' to a conglomerate led by Moscow based Zarubezhvodstroy OJSC and SSJV Projects from India.