NTPC, in its board meeting on 31 July 2006, revised upwards its target capacity addition for the XI Plan period (2007-12). The central power PSU will now target to add 21,941 MW of additional power capacity that is 26 per cent higher than the originally targeted 17,333 MW. The revised target is subject to allocation of state governments and obtaining statutory approvals.

The NTPC board also approved an investment of Rs.2,883 crore towards setting up the 500 MW Farakka Super Thermal Power Project (Stage III) as a merchant power plant. Besides, an investment of Rs.5,596 crore was approved towards Stage II (2x490 MW) of the National Capital Power Station at Dadri in Uttar Pradesh.

The capacity addition in the XI Plan period will come from 23 projects -- both thermal and hydropower. The total capacity of these projects will be 28,201 MW out of which 21,941 MW will be commissioned by the end of the XI Plan period (March 2012).