NTPC plans inter bus transformers at Rihand power plant Illustrative image – not actual.

NTPC is planning to install inter bus transformers for its Rihand super thermal power project in Sonebhadra district of Uttar Pradesh.

 

For the purpose, the company has invited bids from eligible bidders. The scope of work involves supply, erection and commissioning of 400kV/132kV/ 33kV transformers with 200 MVA capacity at the specified plant. The work is expected to be completed within 15 months.


The company is setting up 1,000 MW Rihand super thermal based power unit in two phases with an estimated investment of Rs 6,230 crore. NTPC has commissioned one unit with 500 MW capacity in November 2012.


Related Link:
Project profile

← All latest storiesBack to top →