NTPC plans captive port for Marakkanam plantIllustrative image – not actual.

NTPC proposes to set up a captive port at Marakkanam in the Viluppuram district of Tamil Nadu to facilitate supply of coal to its 4,000 MW imported coal based thermal power project coming up there.

NTPC has already completed feasibility studies for the construction of a deep-water open jetty at the proposed site, to receive up to 10 million tpa of coal from overseas collieries. NTPC has now sought clearance from the Tamil Nadu Maritime Board to commence construction activities.

The power project is to be developed in two phases, consisting of two 1,000 MW units, each. The land requirement for the project has been estimated to be 3,000 acre, which will be utilised for the development of the main plant, township, ash disposal zone and other associated facilities.

Also See:

NTPC to relocate 3,960 MW project to MP (22-May-10)

Related Links:
Project profile

← All latest storiesBack to top →