Illustrative image – not actual.NTPC has outlined capital expenditure of Rs.11,325 crore during 2006-07 that would be 57 per cent higher than its comparable level of Rs.7,188 crore in 2005-06. In 2004-05, NTPC made capital expenditure of Rs.5,360 crore.
In the first four years (2002-03 to 2005-06) of the X Five Year Plan, NTPC added fresh power capacity worth 4,000 MW taking the company's aggregate installed capacity to 24,249 MW (including 314 MW of the NTPC-SAIL joint venture). In 2005-06, NTPC added 500 MW by the commissioning of Unit 4 of the Rihand Stage II (2x500 MW) in September 2005.
Construction work on projects envisaging total capacity of 9,470 MW is in progress, while another 3,720 MW is under bidding process. NTPC has targeted to add fresh power capacity of 26,000 MW during the X and XI Plan periods.
|
NTPC's
Capacity Addition |
|
| Status | MW |
| Commissioned | 4,000 |
| Under construction | 9,470 |
| Bids received | 3,720 |
| FRs/DPRs prepared | 5,101 |
| FRs/DPRs under preparation | 4,445 |
| Total | 26,736 |
NTPC has targeted to achieve total capacity of 46,000 MW by March 2012 and 66,000 by 2017.