NTPC, OTPCL to develop thermal power plantIllustrative image – not actual.
NTPC and Odisha Thermal Power Corporation (OTPCL), yesterday, agreed to jointly develop a 2,400 MW thermal power plant in Dhenkanal district of Odisha.


It has been decided that NTPC would be a partner in OTPCL's proposed 2,400 MW (3x800 MW) coal-fired power plant to be set up at an investment of Rs 17,000 crore. The proposed unit will come up at Kamakshyanagar, in Dhenkanal distict.


The power project requires 1,767.90 acre of land, of which 1,074.95 acre is private land, 684.25 acre is government land and 8.7 acre forest land. The state government has already accorded administrative approval for acquisition of 982.01 acre of private land at the project site. OTPCL has also obtained water allocation from the department of water resources.


The Tentuloi coal block in Talcher coalfields with reserves of 1,234 million tonne has been allocated for the power plant. The annual requirement of coal is 12.62 million tonne per annum.


The Odisha government has decided to adopt the ultra mega power plant (UMPP) model and induct a strategic partner through competitive tariff bidding for 25 years.


OTPCL, a 50:50 joint venture between state-owned Odisha Mining Corporation (OMC) and Odisha Hydro Power Corporation (OHPC), had hit a roadblock in implementing the project due to lack of expertise. NTPC was therefore urged to participate in the project and agreed to that.


A joint venture between OTPCL and NTPC is expected soon.


NTPC has also been mandated to set up 3,000 MW solar power projects across the state.


The company has also agreed to set up a 1,000 MW solar power station in Andhra Pradesh and a 750 MW one in Madhya Pradesh.

 

More Project Info:
Coal Based Power (Kamakhyanagar) Project