NTPC has reportedly tied up funds to the tune of Rs 22,000 crore from PFC, LIC, domestic banks and financial institutions to finance its capital expenditure for the current fiscal.
The company with all its subsidiaries and JVs is likely to have a total capex of Rs 24,525 crore during the fiscal to finance power generation projects, coal mining business, renovation and modernisation activity. On a standalone basis, NTPC is expected to invest Rs 17,700 crore during this fiscal. The company with its JVs and subsidiaries will add 3300 MW during FY10.
Besides, the company's four power projects are slated to be commissioned in this year — Sipat Stage I (2x660 MW), Dadri Stage II (2x490 MW), Kahalgaon Stage II and Korba Stage-III, 500 MW each.
The company also plans to develop its own coal mines at Pakri Barwadih in Jharkhand. Currently, the land acquisition for the block is on and is likely to be completed by November 2009.