Illustrative image – not actual.NTPC and L&T are seeking to acquire stake in the 2,400 MW coal-based power plant at Kamakhyanagar in Dhenkanal district of Orissa.
The proposed 2,400 MW (3X800 MW) project is being set up by Orissa Thermal Power Corporation (OTPCL), a 50:50 JV between Orissa Mining Corporation (OMC), and Orissa Hydro Power Corporation (OHPC), with an investment of Rs 10,000 crore. Both, NTPC and L&T are looking to acquire upto 49 per cent stake in the project.
The project will require 1,969.78 acre of land which includes 987.77 acre of government land, 83.94 acre of forest area and 982.015 acre of private land. The state government has received administrative approval for acquisition of 982.015 acre of private land at the project site.
Meanwhile, the company has secured water allocation from the department of water resources. Also, the inter-ministerial committee (IMC), on coal has recommended the Tentuloi coal block with 1,234 million tonne reserves in favour of the state PSU.
Related Link:
Project profile