Illustrative image – not actual.NTPC is facing delay in the Barh coal-based power project in Patna district of Bihar as the equipment vendors have been delaying supplies.
Russia's JSC Technoprom Export (TPE) and Power Machines are the equipment vendors of the project.
The entire project is being developed by NTPC in two stages. Stage-I of the project comprises three units, each with 660 MW capacity, while Stage-II of the project comprises two units, each with 660 MW capacity. Stage-I of the project is estimated to cost Rs 8,693 crore.
Due to a delay in supply of the equipment, the commissioning of Stage-I of the project will be affected. Unit-I of the project is now expected to be functional in November 2015, a delay of more than two years. Unit-II, which was to be commissioned by March 2014, is now expected to be completed by July 2016. Unit-III of Stage-I may only be completed by March 2017, as against the earlier agreed date of September 2014.
The delays were due to financial constraints faced by the Russian firm.