Illustrative image – not actual.The Union power ministry has directed NTPC to expand the capacity of its existing Farakka thermal power station in West Bengal from the existing 1,600 MW to its approved capacity of 2,100 MW. The ministry has asked NTPC to commence work on the project so as to achieve completion by 2009.
NTPC has been going slow on the expansion in view of shortages of coal and water. The ministry has suggested that the increased water requirements could be met from the Farakka feeder canal on River Ganga. Additional coal could be made available by exploiting the vast reserves of the Brahmani coal mines in Orissa.
Incidentally, the Farakka expansion plan does not feature in the NTPC board-approved list of projects to be taken up till March 2007.
The Farakka thermal power plant located at Murshidabad in West Bengal currently has capacity of 1,600 MW arising from two units of 500 MW and three units of 200 MW.