Illustrative image – not actual.National Thermal Power Corporation (NTPC) has deferred a proposal to clear Bharat Heavy Electricals Ltd (BHEL’s) reduced capital costs of its 1,000 MW Rihand and 500 MW Ramagundam power projects, as NTPC wants the cost lowered further. These projects are coming up at Uttar Pradesh and Andhra Pradesh, respectively.
NTPC had awarded the EPC contracts for both projects
to BHEL, who was the sole bidder in both cases. BHEL had quoted a price of
Rs.2,375 crore for the Rihand project and Rs.1,315 crore for the Ramagundam
project. Later, NTPC had negotiated and reduced the cost to Rs.2,090 crore and
Rs.1,176 crore.
The reduction in cost was brought about through
negotiations, a five per cent reduction in capital cost for each project, by
BHEL and NTPC’s agreement to take up the civil works component for the projects
at lower rates of Rs.215 crore for Rihand (as compared to BHEL’s Rs.361 crore)
and Rs.150 crore for Ramagundam (as compared to BHEL’s Rs.215 crore).
Not satisfied, NTPC has deferred the clearance of the
capital cost in an attempt to further reduce the same.