Illustrative image – not actual.NTPC has commissioned the seventh unit of 500 MW of its Ramagundam super thermal power project at Karimnagar district in Andhra Pradesh. The overall capacity of the power station now stands at 2,600 MW.
The project was completed in a record 37 months. Coal linkages 2.5 million tonnes per year have been firmed up with Western Coalfields.
NTPC has aimed at adding 9,370 MW of additional capacity during the ongoing Tenth Plan period (2002-07) and 11,588 MW in the Eleventh Plan (2007-12).
During the Tenth Plan period so far, NTPC has already commissioned 2,000 MW of fresh capacity. While 8,490 MW worth of capacity is under various pre-project stages, the tendering process has begun for 5,080 MW worth of capacity. NTPC is confident of attaining the targeted capacity addition.
In another development, NTPC has initiated a dialogue with Petronas of Malaysia for sourcing natural gas of around 7-9 mmscmd for its existing gas-based power plants at Anta, Auriya, Kawas, Gandhar, Dadri and Faridabad.