Illustrative image – not actual.NTPC has successfully commissioned Unit VII of 500 MW capacity at Kahalgaon Super Thermal Power Station in Bihar.
The power station mainly supplies power to the states of Eastern, North Eastern, Northern and Western regions of the country. Coal for the power station is obtained from Eastern Coalfields.
Earlier, NTPC has commissioned three units of 210 MW and two units of 500 MW capacity each at the power station. With the commissioning of Unit VII, the total installed capacity of the power plant is expected to reach 2,340 MW.