Illustrative image – not actual.NTPC and Bihar State Electricity Board have floated a joint venture company - Bihar Bijli Company, Nabinagar - for setting up a 1,980 MW coal-based power project at Nabinagar in Aurangabad district of Bihar, with an investment of Rs.9,000 crore.
Work on the proposed project will start by March 2008 and the first unit of 660 MW will be commissioned within a period of 51 months. It is learnt that, around 75 per cent of the power generated in Nabinagar will be allocated to BSEB and the rest 25 per cent will be allocated to the joint venture company.
Both the companies had signed a 50:50 joint venture agreement for the purpose in October 2007.