NTPC board clears Rs.7,244.9 crore investment proposalsIllustrative image – not actual.

On 26 November 2007, NTPC board cleared investment proposals worth Rs.7,244.9 crore, which includes:

  • Setting up a 2x500 Mw coal-based power plant at Mauda in Amravati district of Maharashtra, with an investment of Rs.5,459.3 crore.
  • Renovation and modernisation of a 645 MW gas-based power plant at Kawas in Gujarat, with an investment of Rs.597.4 crore.
  • Picking up majority stake (74 per cent) in the joint venture company with the Indian Railways - Bhartiya Rail Bijlee Company (BRBCL) - by investing Rs.1,188.2 crore, for the implementation of Nabinagar Thermal Power Project (4x250 MW) in Bihar.