Illustrative image – not actual.Ispat Energy
Ltd has mandated National Thermal Power Corporation (NTPC) as the operations
and maintenance (O&M) contractor for its short gestation 110 MW captive
power project at Dolvi in Maharashtra. The O&M contract envisages
development of operating procedures, standing instructions and computerised
O&M management system.
The project, which is being implemented by a special purpose
vehicle – Ispat Energy Ltd, involves relocation of
the units from Richmont, France, where they were operated with blast furnace
gas. The plans for refurbishment, renovation and mordernisation have been
worked out in consultation with original equipment manufacturers and
engineering consultants. The dismantling of the units in France is almost
complete and the units would be shipped shortly.
The plant will
utilise gas from Ispat Metallics’ blast furnace, which has a capacity of the
two million tonnes per annum of hot metal. The power plants will have two units
of 55 MW each having blast furnace drum type boilers, two stage steam turbine
and air-cooled generators. IDEA, a unit of Deutsche Babock, Germany, which is
the equipment manufacturer for the boilers and the engineering consultant, has
completed the engineering work for the plant. The land required for the project
has been acquired and the land development work has been completed. All the
statutory clearance from MSEB (under section 44 of ESA 1948), Airport
Authority, and the power purchase agreement has been finalised.
According to
reports, the relocation of the units would be beneficial due to a short
gestation period and lower capital cost. The gestation period for the two units
would be about 12 to 14 months from the date of financial closure,
respectively, as against 24 to 30 months for a new plant of a similar
configuration.