Illustrative image – not actual.The process for obtaining the necessary clearances for NTPC's proposed Darlipalli thermal power plant as well as for its linked Dulanga coal mine in Orissa is underway.
The process to obtain environment and forest clearance from the Ministry of Environment and Forests is in progress for both of these projects. Environment clearance for the project was recommended by Expert Appraisal Committee (EAC), of the Environment Ministry last year, subject to grant of forest clearance for 1,600 MW Darlipalli project and environment and forest clearance for linked Dulanga coal mine. For forest clearance of 34.47 acre of forest land of the Darlipalli project, Forest Advisory Committee (FAC) of the Environment Ministry had recommended a decision on diversion of forest land required for these two projects.
Also, the process of land acquisition by the state government is underway. Out of the 1,274 acre of private land, the possession certificate has been received for 1,205 acre, and of the 338.97 acre of government land, NTPC has released payment for 275 acre. Transfer of government land is under process for approval of the state government.
The proposal for diversion of forest land for Darlipalli project with Environment Ministry should be transferred to FAC for consideration along with the Dulanga proposal.