Illustrative image – not actual.The Karnataka state government has initiated talks with National Thermal Power Corporation (NTPC) for participation in the Vijaynagar power project in Karnataka.
According to the original plan, Larsen & Toubro
(L&T) was to pick up 25 per cent equity in the power project. But, L&T
laid certain pre-conditions, viz. award of the EPC contract to it, prior to
picking up equity. This was not acceptable to Karnataka Power Corporation Ltd
(KPCL), the lead implementing agency of the project. KPCL preferred following
the Electricity Regulatory Authority’s guidelines and using the bidding route
for the selection of the EPC contractor.
KPCL proposes to set up the project with a total
capacity of 720 MW in two phases in Karnataka, using naphtha as fuel. It may be
recalled that the original plan envisaged a capacity of 500 MW with gas as
fuel.