Illustrative image – not actual.
NTPC has acquired Barauni Thermal Power Station from the Bihar State Power Generation Company (BSPGCL) in Begusarai district of Bihar on 15 December 2018.
The 720 MW coal-based power station has two units of 110 MW each under renovation and modernisation and two units of 250 MW each under construction.
The units of the power station will be progressively put under commercial operation. The project has linked Badam Coal Block, which is also part of the transfer scheme.
The transfer has been completed in accordance with the Bihar Power Generation Undertakings Transfer Scheme 2018, notified by the government of Bihar on 27 June 2018 and amendment dated 14 December 2018.
The entire capacity of the project is tied up through Power Purchase Agreement with Bihar Power Discoms.