Ntimbale Dam Water Supply Scheme on trackIllustrative image – not actual.
The Ntimbale Dam Water Supply Scheme upgrade and remedial works project is on track in the North East District and Tutume sub-district, Botswana.
 
The USD 20.4 million project which commenced in March 2020 is 47 percent complete against the planned 60 percent as on 23 February 2021. 
 
The delay in the project is due to COVID-19 challenges such as lockdown which was imposed immediately after the project started, delays in receipt of materials needed for the project due to travel restrictions. 
 
By April 2021, construction will commence on building reserve tanks across identified sites in Tutume, Goshwe, Maitengwe and Makuta. 
 
The project is expected to be completed September 2021.

 

← All latest storiesBack to top →