Illustrative image – not actual.The Nuclear Power Corporation of India Ltd's (NPCIL) two new units of the Rajasthan Atomic Power Station (RAPS) are expected to commence operations by January 2010.
According to sources, NPCIL is likely to get the clearance for the use of imported fuel in the reactors from the International Atomic Energy Agency (IAEA) shortly, following which the fifth unit could be commissioned as early as November 2009 and the sixth by January. Nuclear fuel received from Areva of France will be used in the two units, which are both Pressurised Heavy Water Reactors of 220 MWe capacity.
Both the units are expected to come under the IAEA's India-specific safeguards that will allow them to qualify for running on imported uranium.
As per the earlier schedule, the fifth unit was to commercial operations in August 2007 and the sixth unit in February 2008. However, fuel shortages had held-up the commissioning of both the units at RAPS, as well as a new unit at Kaiga (unit fourth) in Karnataka.
In early September 2009, NPCIL had synchronised the second unit of 200 MWe capacity of the RAPS using the uranium supplies from France, making it the first reactor unit to be operated using the fuel consignments received after the NSG waiver.