Illustrative image – not actual.Nuclear Power Corporation has decided to advance the commercial commissioning of Unit 4 (540 MWe) of its Tarapur atomic power plant, by a month. The unit is expected to begin commercial operations by 15 May 2005.
The unit, which is the largest power unit of any kind in India, went critical on 6 March 2005. The project was completed seven months ahead of schedule, and within five years from the first pour of concrete.
NPCIL has expedited the commissioning of the power plant with a view to help Maharashtra, which would get 39 per cent of the power produced, to tide over its present power crisis.