Illustrative image – not actual.Nuclear Power Corporation of India intends to set up 16,900 MW of extra nuclear capacity at an investment of Rs.1,01,400 crore ($23.03 billion) during the XI Plan.
NPCIL has sought the government approval for its ambitious capacity addition programme. The proposal includes setting up eight nuclear reactors of 700 MW capacity. Two of these have been proposed at NPCIL's existing site in Gujarat's Kakrapar, while another two may come up in Rajasthan. The location for the other four reactors is yet to be decided.
NPCIL has started pre-project activities for two additional fast-breeder reactors at Kalpakkam. These are part of the expansion proposal submitted to the government. The company has already initiated the process of setting up one fast-breeder reactor, scheduled to go critical by March 2011.
Additionally, the company, as part of the proposal, plans to set up 300 MW advanced heavy water reactors. Conceptual design for the plant is complete but the location is yet to be decided.
Finally, the proposal includes plans to set up 10 large capacity reactors of 1,000 MW each. These are likely to be built with imported technology, and four each will be set up at Tamil Nadu and Maharashtra. The location of the remaining two are yet to be decided. The remaining two will come up at any of the four new sites that the Site Selection Committee is considering. These include sites in West Bengal, Gujarat, Orissa and Andhra Pradesh.