Illustrative image – not actual.Nuclear Power Corporation of India (NPCIL), has postponed the expected date of commissioning of Unit-I of the Kudankulam Nuclear Power Plant in Tamil Nadu, to July 2013.
Unit-I of the project has 1,000 MW capacity, and around 99.67 per cent work on the unit has been completed so far. Unit-II, of which around 94.52 per cent has been completed, was expected to be commissioned in March 2014 but the commissioning date has been postponed every month.
NPCIL is developing the entire project with 2x1,000 MW capacity at Kudankulam in Tirunelveli district of Tamil Nadu. The project is estimated to cost Rs 17,270 crore.