NPCIL to commission eight projects over three yearsIllustrative image – not actual.

Nuclear Power Corporation of India has planned to commission eight new projects over the next three years. With this, total installed capacity is expected to rise to 7,270 MWe from the existing 2,270 MWe by 2008.

The projects in question are:

Plant State Capacity (MWe) Expected Completion
Tarapur - III MAH 540 Oct-05
Tarapur - IV MAH 540 Jul-06
Kaiga KAR 220 Dec-06
Kaiga KAR 220 Jun-07
RAPS-V RAJ 220 May-07
RAPS-VI RAJ 220 Nov-07
Kudankulam-I TN 1000 2007
Kudankulam-II TN 1000 2008

The long term plan of NPCIL is to attain 20,000 MWe by 2020.