NPCIL: Annual review of 2000-01Illustrative image – not actual.

The following are highlights of Nuclear Power Corporation of India’s performance in 2000-01.

 

  • NPCIL commissioned four nuclear units during 2000-01, the highest so far, in any one-year period. The units in question are Kaiga (Units 1 and 2) in Karnataka and Rajasthan Atomic Power Plant (Units 3 & 4).
  • During the year, NPCIL received budgetary support of Rs.586 crore to meet capital expenditure and credit of Rs.134 crore from Russia. Besides, the company raised Rs.659.50 crore from the capital market and Rs.145 crore through Infrastructure Bonds.

 

Status of on-going projects:

 

With regard to projects under implementation, the company has hastened the construction activity at the two units of the Tarapur Atomic Plant. Accordingly, criticality is expected to be reached by 2005-06 as against 2006-07. Further, the rated capacities of these two Tarapur units has been scaled up from 500 MWe to 540 MWe.

 

The techno-commercial offer for setting up of two units of VVER type reactors, at Kudankulam, with Russian collaboration has been negotiated and contracts are expected to be signed shortly. Pre-project work is progressing satisfactorily.

 

The Union government has accorded project financial sanction in May 2001 for setting up of two units each of 220 MWe at Kaiga (Units 3 and 4). The excavation work for these units has commenced and work on tendering contracts for major packages has been initiated.

 