Illustrative image – not actual.The following are highlights of Nuclear
Power Corporation of India’s performance in 2000-01.
- NPCIL commissioned four nuclear units during 2000-01,
the highest so far, in any one-year period. The units in question are Kaiga
(Units 1 and 2) in Karnataka and Rajasthan Atomic Power Plant (Units 3
& 4).
- During the year, NPCIL received budgetary support of
Rs.586 crore to meet capital expenditure and credit of Rs.134 crore from Russia.
Besides, the company raised Rs.659.50 crore from the capital market and
Rs.145 crore through Infrastructure Bonds.
Status of on-going projects:
With regard to projects under
implementation, the company has hastened the construction activity at the two units
of the Tarapur Atomic Plant. Accordingly, criticality is expected to be reached
by 2005-06 as against 2006-07. Further, the rated capacities of these two
Tarapur units has been scaled up from 500 MWe to 540 MWe.
The techno-commercial offer for setting
up of two units of VVER type reactors, at Kudankulam, with Russian
collaboration has been negotiated and contracts are expected to be signed
shortly. Pre-project work is progressing satisfactorily.
The Union government has accorded
project financial sanction in May 2001 for setting up of two units each of 220
MWe at Kaiga (Units 3 and 4). The excavation work for these units has commenced
and work on tendering contracts for major packages has been initiated.