NPC Tarapur plant: Fuel loading beginsIllustrative image – not actual.

Nuclear Power Corporation of India has begun loading of natural uranium fuel bundles for the fourth unit its Tarapur Atomic Power Plant (TAPP-4) in Maharashtra. There are 392 channels to be loaded, each of which will take 13 bundles. The fuel loading process is expected to be completed by end-January 2005. The plant is likely to reach criticality in February 2005.

TAPP-4 is India's largest pressurized heavy water reactor (PHWR) of 540 MWe. It is being developed ahead of TAPP-3 that is also under construction.

Related News:

TAPP-4 nears completion (27-Jul-04)

NPCIL to commission eight projects by 2008 (23-Nov-04)

← All latest storiesBack to top →