Illustrative image – not actual.Nuclear
Power Corporation of India (NPC) has sought relaxations in the Atomic Energy
Commission Act to facilitate participation of the private sector in the nuclear
(atomic) power sector. This would help NPC in realising its target of attaining
a capacity of 20,000 MW by the year 2020.
Although NPC is capable of funding its
projects through internal accruals, the participation of the private sector
would reduce the financial burden on the company in the long run.
Meanwhile, the Kudankulam (Tamil Nadu)
project was stated to be in an advanced stage of implementation. The 2,000 MW
project entails the construction of two reactors of 1,000 MW each. The cost of
the project is estimated at Rs.14,000 crore (or Rs.7 crore per MW). NPC is in
the process of rationalising the costs to around Rs.6.6 crore per MW. Russia,
which would be providing technological input, has agreed to extend a soft loan
of 54 per cent of the project cost at an interest rate of 4 per cent. The loan
will be repayable in 14 equal installments starting from the second year after
commissioning the plant.
The first unit of 1,000 MW is expected
to be commissioned by 2007, while the second would follow in the subsequent
year.