Northern Water Collector Tunnel to be operational by 2020-endIllustrative image – not actual.
The Northern Water Collector Tunnel is expected to be operational by the end of 2020. The project worth USD 66 million is being funded by the World Bank.

The tunnel is touted to solve Nairobi city’s water issues by increasing water supply to the city via Ndakaini dam to a capacity of 1,40,000 cu mtr per day.

Around 89 percent excavation, which accounts to 11.4 km out of the entire 12.7 km, has been completed and the remaining 1.3 km that will connect Ichichi intake area of Kangema Sub-County to Ndakaini dam will be complete by the end of 2019.

After the tunneling work is done, work will commence on water treatment plant and laying of pipelines from Ndakaini to Nairobi at a cost of USD 45 million. All this work will take at most one year to complete.

The entire Northern Water Collector Tunnel project involves construction of river intake structures at Maragua, Gikie and Irati rivers plus construction of access adits at Gikigie, Irati and Kaanja. It also involves construction of a fully concrete lined 11 km long, 3.0 diameter main water tunnel from Maragua intake to Githika outfall.

The tunnel is set to collect only flood water from the three rivers and it will therefore not interfere with normal flow of the rivers. A Nairobi city water distribution network will be constructed as well to ensure equitable distribution, and lastly, improvement of water services in Nairobi satellite towns within Kiambu and Kajiado counties.