Illustrative image – not actual.The Northeast Frontier Railway has invited two separate bids in connection with new BG line in Manipur. This includes:
Construction of substructure of bridge no 134 (2x71.50 mtr) at 71.463 km, bridge no 136 (2x71.50 mtr + 2x30.00 mtr) at 73.163 km, bridge no 138 (3x30.00 mtr) at 73.91 km, bridge no 147D (1x30.00 mtr) at 83.26 km, bridge no 174 (3x30.00 mtr four-line track) and chum test of piles of bridges no 148, 169A, 169B, 169C, 171, 172 and 174 including other ancillary works in connection of construction new BG line from Jiribam to Imphal project.
The estimated cost of the project is Rs 150.03 crore with completion period of 18 months.
Providing, surface preparation and applying of high performance water-based anticarbonation protective coating over the prime coat to the piers/abutments of tall major bridges and major viaducts, etc and other locations of section in between Ch 9.00 km to 72.0 km (up to bridge no-130) in connection with construction of new BG railway line from Jiribam to Tupul (Imphal).
The estimated cost of the project is Rs 10.6 crore with completion period of eight months.