Illustrative image – not actual.Noida Authority has agreed to provide complete funding for the two proposed substations in Uttar Pradesh to speed up their completion.
Noida Authority will fund 400 KV substations in Sectors 123 and 148. Foundation stone for the projects has been laid by Akhilesh Yadav, Chief Minister of Uttar Pradesh. The total cost of both the projects, including their transmission lines, is estimated at Rs 1,548 crore and will be released by the Authority in a series of installments.
Work on the projects is in indeterminate state due to non-availability of land and then over lack of funds, the city has been experiencing massive outages. The two new substations will supplement the 400 KV substation in Pali, which is the only source through which both Noida and Greater Noida receive power at present. Work on the projects will be completed under the vigilance of the Uttar Pradesh Power Corporation.