No SPV for Bangalore Metro Rail projectIllustrative image – not actual.

The Planning Commission has decided that the Bangalore Metro Rail Corporation (BMRC) should finance the project with grants from the government instead of going through the 50:50 equity model that involved setting up a special purpose vehicle (SPV) for the funds.

The project, estimated to cost Rs.6,395 crore, has a debt-equity ratio of 70:30. As per the current funding model, the Centre and the Karnataka government are to contribute 15 per cent each to the equity portion. For the debt portion, 45 per cent will be taken care of by the BMRC in the form of borrowing from the Japanese Bank for International Cooperation (JBIC) and the remaining 25 per cent will be raised through subordinate debts. The JBIC is providing the loan at an interest rate of 8.75 per cent per annum.

According to the MoU signed with JBIC, the Japanese bank will give a loan of Rs.1,795 crore for the project under a special rate of interest. While the bank charges an interest rate of mere 1.3 per cent per annum the project will have to bear a rate of 3.6  per cent.

The proposed metro project envisages a 33 km elevated and underground rail network with 32 stations in the first phase. The proposed gauge will be standard gauge, unlike the broad gauge in the Delhi Metro network. The BMRC, executors of the project, has the Delhi metro as its consultant.

Construction work, which was scheduled to start in 2005, was delayed due to change in the coalition government in the state and continuous debate over the feasibility of the project. In April 2006, the UPA government cleared the project, which was likely to be fully commissioned by 2011.