Illustrative image – not actual.The berth is being constructed at a cost of Rs 469.46 crore. At present, coal-handling is semi-mechanised at the port. With the commissioning of the new berth, the operations will be mechanised end-to-end. The multi-purpose Berth 14 will be developed as a container terminal.
The request for quotation (RfQ) for it is over now. The request for proposal (RfP) to mechanise the berth will be issued soon, and the proposal will be sent to the government for clearance.
The project will be taken up in two phases with an investment of Rs 280.71 crore. After awarding the project to the successful bidder, Phase-I will be completed in 18 months.
Apart from this, NMPT is planning to develop Berth 17 as a multi-purpose berth with an investment of around Rs 200 crore from its own resources. Berth 17 will be ready for handling multi-purpose cargo by the time Berth 14 is ready for handling container cargo in two years.
NMPT is planning to take up dredging to maintain a uniform draft of 14 mtr throughout the year in the channel. IIT Madras will work out the economic feasibility of increasing the draft to attract bigger vessels.