Illustrative image – not actual.NMDC has decided to change the location of its proposed power plant from Gonda district in Uttar Pradesh.
The company will shift its 500 MW power project in view of the objections raised by the Expert Appraisal Committee (EAC) under the Ministry of Environment & Forests.
The consultant of the project, Mecon, has come up with three alternative sites within and outside Gonda with the help of Topo Sheets and Satellite imageries.
The EAC has asked the company to prepare a detailed plan with regard to the environmental issues on the site at Turkadih-Siswa.
Earlier, EAC refused to give the green nod for the project, stating that the location for the proposed project was fertile agriculture land, and asked the company to come out with alternative lands.
Once the detailed project report gets prepared, the company will take an investment decision on the project.