Illustrative image – not actual.NMDC is setting up a three million tpa greenfield integrated steel plant in Nagarnar, about 16 km from Bastar’s divisional headquarters at Jagdalpur. The project is part of NMDC’s diversification, value addition and forward integration programme.
The company plans to feed raw material to the plant from its iron-ore complexes located in Bastar division. NMDC manages two fully mechanised mines with a capacity of 25 million tpa in Dantewada district of Bastar. The Nagarnar steel plant was conceived by NMDC in 2009-10 and the contract to build raw material handling system was awarded to BHEL on 1 August 2011.
The estimated cost of the project was Rs 1,395 crore and was stipulated to be completed by 28 February 2014. BHEL failed to expedite the contract. Even after continuous follow-up at corporation and ministry level, BHEL did not accelerate the progress of the project, resulting in delay of over five years.