Neyveli Lignite Corporation (NLC) proposes to raise its power generation capacity from the present 2,490 MW at an outlay of Rs 9,900 crore.
NLC is mulling to set up 2,000 MW power plant between Tuticorin and Chennai. The company requires around 2,000 acre for the project and has asked the Tamil Nadu Government to allocate land.
Also, Phase I and Phase II (each 125 MW) project in Rajasthan will go on stream in June and Jul 2010 respectively. NLC plans to add another 500 MW in Rajasthan.
NLC is also planning to set up wind farms in the districts of Tiruneveli and Theni in Tamil Nadu, with a total capacity of 50 MW. A solar power plant is also being proposed in Neyveli with a capacity of 25 MW.