Illustrative image – not actual.Neyveli Lignite Corporation and Tamil Nadu Electricity Board have floated a joint venture -- NLC Tamil Nadu Power Ltd -- to implement a 1,000 MW greenfield power project. NLC will be the majority shareholder with 89 per cent equity with TNEB holding the remaining 11 per cent.
The coal-based project costing Rs.4,500 crore will come up at Tuticorin, in the vicinity of TNEB's existing thermal power station. Land for the project will be provided by Tuticorin Port Trust on long-term lease.
Targeted for completion in 2010-11, the power plant will have two units of 500 MW, and will supply power mainly to Tamil Nadu, and to Karnataka, Kerala and Pondicherry.
The coal requirement for the power plant, estimated at five million tonnes annually, will be sourced from Talcher Coalfields in Orissa. Some coal will also be imported for blending.
The project proposal will be soon submitted to the Centre for clearance, it is learnt.