NLC India in process to execute 11 GW power projectsIllustrative image – not actual.

Lignite and power major NLC India (NLCIL) is in the process of implementing power projects comprising thermal and solar with a total capacity of over 11 GW. The firm is planning to add nearly 5.6 GW of solar capacity through seven projects across the country.

These projects are expected to be commissioned from March 2024 to FY28. These renewable energy (RE) projects include a 600 MW solar project at Khavda from Gujarat State Electricity Corporation (GSECL) solar park tender (300 MW plus 300 MW under Greenshoe option), a 1,000 MW solar power project in Assam through joint venture (JV) mode, and an 810 MW solar project from Rajasthan Rajya Vidyut Utpadan Nigam (RRVUNL), among others.

NLCIL is also implementing 5.7 GW of coal-fired projects, which include the 1,980 MW project of Neyveli Uttar Pradesh Power (NUPPL), a joint venture (JV) between NLCIL and UPRVUNL Ghatampur Thermal Power Project (GTPP), 2,400 MW of NLC Talabira Thermal Power Project (NLTTPP) and 1,320 MW lignite-based thermal power project-II (TPS-II) expansion.

As part of its diversification plans, the company has also been working on a lignite-to-methanol project of 0.4 mtpa capacity at Neyveli, Tamil Nadu. The Rs 4,394 crore project, which will require 2.26 MTPA lignite, is expected to be completed by March 2027. The estimated capex for these thermal projects is about Rs 50,000 crore. While the first project is expected to be commissioned by March 2024, the other two thermal projects are anticipated to be operational by March 2029.

The business targets to achieve 17 GW by 2030. Of the proposed capacity, thermal capacity will reach 11 GW from 4.6 GW now, while total renewable capacity will grow to six GW from 1.4 GW. The firm also intens to boost the mining capacity to 82 million tpa by 2030, up from 50 million tpa now. At present, it is implementing 12 million tpa projects, which will be commissioned between March 2024 and March 2026.
 