NLC India (NLCIL) has completed 72 hours of continuous trial operation of 500 MW of Unit-2 of two x 500 MW pit head lignite-fired Neyveli New Thermal Power Project (NNTPP) at its rated capacity on 3 February 2021.
The 500 MW capacity lignite-fired boilers of NNTPP are the first-of-its-kind in India. The Unit-1 of the project was already commissioned and with this, the power plant will be fully commissioned.
The formal clearance from the Southern Regional Load Despatch Centre (SRLDC) is in process for declaration of commercial operation of the unit. The steam generator and turbine generator packages are executed by BHEL.
With this commissioning of Unit-2, the total installed power generation capacity of NLC India Group increased to 6,061.06 MW.
The states of Tamil Nadu, Kerala, Karnataka, Andhra Pradesh, Telangana and Puducherry are beneficiaries of this station.