NLC India achieves critical milestone for Neyveli Thermal Power ProjectIllustrative image – not actual.

NLC India has achieved a critical milestone towards commissioning its Neyveli New Thermal Power Project. The 1,000 MW (2X500 MW) project successfully conducted the boiler light-up test for the first unit with secondary fuel on 28 December 2018 at Neyveli in Tamil Nadu.

This is the first 500 MW lignite fired power plant in the country. It can generate 10,00,000 units of power in an hour. This power project will replace the existing more than five decades old TPS-I (600 MW) at Neyveli.

The Unit-I boiler hydro test was completed on 22 August 2018 and boiler light up successfully conducted on 28 December 2018 within a span of four months against target of six months.

With the successful conducting of boiler light-up test, the boiler is now ready for power generation process and the company has commenced the work for steam blowing and synchronization of the unit well within the scheduled timeline.

The power purchase agreement (PPA) for the project were signed with Electricity Boards of Tamil Nadu , Kerala, Karnataka, Telangana, Andhra Pradesh and Puduchchery states. Sixty five percent of power generation will be supplied to Tamil Nadu Generation and Distribution Corporation (TANGEDCO) of Tamil Nadu.