The Prime Minister's Office (PMO) has asked NITI Aayog to prepare a report on stalled hydroelectric power projects which have held up large-scale investment.
The government think-tank has also been asked to include the reasons for the projects getting delayed in its report. NITI Aayog has been asked to prepare the report within three months.
The proposed hydro capacity addition during the 12th Plan period is 10,897 MW. However, up to December 2015, the actual capacity addition is only 3,651.02 MW which is 33.5 per cent of the proposed capacity addition, as per government sources.
Of the country's total installed capacity of 2,84,303.39 MW as on 31 December 2015, large hydro capacity is 42,623.42 MW and small hydro capacity is 4,147 MW.